Uitspraak
AMSTERDAM DISTRICT COURT
29 June 2022
1.Procedural history
2.The facts
inter alia,operates wind power plants in Türkiye. [A] (“ [A] ”) is CEO and shareholder of [X] . [A] owns several energy related businesses in Türkiye and in Germany, including [BV 1] ( [BV 1] ), a German manufacturer of wind turbines.
has obtained or will obtain all necessary approvals, permits, licenses and project finance, to build and operate two wind turbine generator(s), type L100-2.5MW (…) at [..] site (…)
has offered to design, produce, deliver, install and commission the WTG('s) (…) at the Site (…)
inter alia, wanted to know when the site would be ready to receive the turbine components and the main crane. [F] also mentioned that the blades would arrive in Türkiye on 17 January 2016. By e-mail dated 25 December 2015, [G] answered as follows:
according to finish your type certificate problem ASAP and reach opening date of the Power plant on 15. April 2016.
has and will provide technical documents to perform its obligations. A Type Certificate is not a technical document. It is not agreed that Contractor would supply Employer[the Court: [X] ]
with a Type Certificate. Employer knows since 2013 that the Plant will be built and the need for a Type Certificate has not been discussed before. Employer has requested the DECS two months ago which has been provided (…). Contractor is not in breach of contract and confirms to keep fulfilling its obligations under the agreement. (…)."
asks you not to take any actions that will lead to additional costs (e.g. shipment of generators) without his prior consent for now. It seems the lack of type certification might turn out to be a serious issue for the realization of the [..] project. However, I am told we have acquired two new projects in Germany that are RTB and might be a good fit for your WTGs.
3.The claim
4.The counterclaim
5.Discussion
stressedthe alleged necessity of a Type Certificate numerous times prior to December 2015. Not every reference to a "certificate" or "certification" relates to a Type Certificate. Therefore, [Y] argues that it did not breach any of its obligations under the Sales Agreement in that respect. On the other hand, [Y] states that [X] itself has repeatedly been in default on numerous occasions, starting even shortly after the Agreements were concluded. The most important breach being [X] 's refusal to take delivery of the generators and other parts of the WTGs. Such (creditor's) default stands in the way of [X] successfully invoking any alleged default on [Y] 's side, according to [Y] .
"(…) We want you to know that both type certificate and all kind of information and documents requested from us for Turkey electricity market regulatory board shall be pursued in time and full through our local company. (…)". [X] disputes that these precontractual statements can be put aside by referring to the entire agreement clause, especially since such a clause does not prevent reliance on the precontractual phase under Dutch law. [Y] , on its part, relies on the entire agreement clause (article 28.6 of the Sales Agreement), which excludes any and all (alleged) warranties, conditions and undertakings which are not reflected in the Sales Agreement.
Lundiform/Mexx), para. 3.5.3 that the meaning of an entire agreement clause under Dutch law will depend on the circumstances of a given case such as the wording of the clause, the nature, content, goal and level of detail of the agreement that contains the entire agreement clause, and the way in which the clause during the negotiations has been discussed and became part of the agreement. The Dutch Supreme Court further added that the usual purpose of an entire agreement clause is that the parties are not bound by earlier agreements which are in contradiction with the contract if those agreements are not contained in the contract and the contract does not refer to those agreements. In essence, this decision of the Dutch Supreme Court implies that the meaning of an entire agreement clause must be determined by interpretation of that clause according to the applicable standard for interpretation under Dutch law.
Haviltex) entails that the question on how a contract provision, such as the entire agreement clause and other provisions in the Sales Agreement, must be interpreted cannot only be answered by looking at the wording of the clause and the linguistic meaning thereof. What is decisive is the meaning which the parties, in the given circumstances, could have reasonably attributed to the provisions in the contract and what the parties could have reasonably expected from each other in that regard. This does not mean that the wording of the clause is irrelevant. Great significance may be attached to the wording, for example in the case of a detailed commercial contract concluded between professional parties each assisted by a lawyer, after intensive negotiations (see the ruling of the Dutch Supreme Court of 19 January 2007, ECLI:NL:HR:2007:AZ3178,
Meyer/PontMeyer). However, although the fact that a contract is a commercial contract concluded by professional parties in the presence of their lawyers and after intensive negotiations about the wording of the contract terms, all other facts and circumstances surrounding the transaction remain relevant and may be decisive. The application of the "Haviltex formula" entailing “all facts and circumstances” of the given case remains decisive, also in the case of a carefully drafted commercial contract (see the ruling of the Dutch Supreme Court of 5 April 2013, ECLI:NL:HR:2013:BY8101,
Lundiform/Mexx). For the sake of clarity, the Court notes that this matrix of facts will only be relevant if and in as far as a party has relied on those other facts and circumstances and has sufficiently substantiated these allegations.
dwangsom), as claimed by [Y] . There is no indication at this time that [X] will not follow the Court's judgment. For that reason, this part of [Y] 's claim will be dismissed.
inter aliarefers to Article 9.2 of the Sales Agreement. [X] also argues that it cannot be held liable for any loss of profit in relation to the Full Service Agreement either, because this agreement has not come into force and has not yet commenced. The Take Over Certificate, mentioned in Article 5.2 of the Sales Agreement, was never signed, nor was the Final Acceptance Certificate, mentioned in Article 1.5 of the Full Service Agreement. Without any further substantiation, it cannot be assumed that the Full Service Agreement would have ever commenced. [X] therefore disputes that it can be held liable for the full EUR 102,113.08.
eigendomsvoorbehoud). Furthermore, [Y] argues that [X] itself had asked [Y] not to move the WTG components. It was only after a long period of time - multiple years - that [X] asked for the WTGs to be delivered to its site in Germany. According to [Y] , the costs incurred in relation to exercising the leverage of a retention title are for the account of the party that breached its obligations.
inter aliastates that [Y] , as [Y] itself explained, applies a "first in, first out" (FIFO) system. This means that the products that are currently stored can just as well be considered as regular, current stock. [X] also points out that [Y] claims EUR 45,902.00 in storage costs only after [Y] 's final amendment of the counterclaim. According to [X] , what stands out is that [Y] has to repay [X] in the counterclaim in every possible scenario.
EUR 14,000.00(3.5 x EUR 4,000.00)