Uitspraak
GERECHT IN EERSTE AANLEG VAN SINT MAARTEN
1.Het verloop van de procedure
2.De feiten
that the works contract of Van Boekel has expired since June 15th, 2020.
Van Boekel hereby also finds legal ground to suspend the works in accordance with 38.3 General Conditions.
- Payment of all submitted invoices (see overview) within several weeks (Note that none of the submitted invoices has been disputed and therefore all approved. Those invoices are extra contractual and therefore not depending on EU terms);
- Clear and unambiguous information about the exact day of payment;
- Full insight, substantiated with proof, of immediate availability of sufficient budget to cover all works, possible additional works and justified claims of Contractor;
- Full insight, substantiated with proof, of actual EoT request and status of EoT at the moment and answer to our question wat the status of our contract agreement is when EoT is not awarded by EU;
- Agreement (in principle) that all damages named in this letter will be compensated as soon as Van Boekel establishes its extent.
by the Contracting Authority’. Deze brief vermeldt:
revised overall planning’ aan VROMI toekomen.
revised overall planning’aan VROMI toekomen.
4.De beoordeling
goed te keurenkan onder de uitzondering van deze bepaling worden gebracht. [7]
voor verricht en uitgevoerd werkbetaald te krijgen. Van Boekel hoeft – het pokopoko beginsel [8] ten spijt – niet langer te dulden [9] dat de toch al lange betalingstermijnen van 90 dagen door het Land nog verder wordt opgerekt. Termijn #6 heeft het Land onbetwist gelaten zodat deze termijn ook hierna op dezelfde gronden wordt toegewezen.