Uitspraak
AMSTERDAM COURT OF APPEAL
1.The procedure
- the initiating document in appeal;
- the grounds of appeal by Meriç, and Exhibit A,
- the statement of defence in appeal and statement of grounds for cross-appeal by Lagerwey, and Exhibits R-44 through R-51,
- the statement of defence in cross-appeal by Meriç, and Exhibits 58 through 64,
- the response to newly submitted exhibits by Lagerwey, and Exhibits R-52 through R-54.
2.The facts
inter alia, operates wind power plants in Turkey. Mr [A] is CEO and shareholder of Meriç. [A] owns several energy-related businesses in Turkey and in Germany. One of these companies is Amperax Energie GmbH. In 2014 Amperax acquired Prokon Regenerative Energien GmbH, a German manufacturer of wind turbines.
8- Taking Over Certificate should be tied to “Wind Farm’s Provisional Acceptance by Ministry of Energy in Turkey”.
during the process with the Ministry of Energy in Turkey. All other major turbine suppliers provide this.”
This is new to us, please explain.”
The wind farm becomes officially operational when its provisional acceptance is completed by Ministry of Energy in Turkey. It is a 2-3 day task where the officials come and inspect the wind farm against projects and specifications submitted before construction and installation. Wind turbine supplier should support the employer during this phase (preparation of the projects/specifications and physical inspection). Physical inspection is 1-2 engineers from LW with power of attorney to sign official documents on site. During the inspection turbines are tested (simple power tests, emergency stop, grid communication etc.). Before this task is completed, the wind farm’s produced energy cannot be sold to the grid. Basically before this happens, the energy is provided to the grid for free. It is normal to tie the final symbolic payment to this milestone.”
Please see item 8.”
Employer[Meriç, the Court]
has obtained or will obtain all necessary approvals, permits, licenses and project finance, to build and operate two wind turbine generator(s), type L100-2.5MW[...]
at Hamzabeyli site[...]
has offered to design, produce, deliver, install and commission the WTG('s)[...]
at the Site[...]
The Agreements shall become effective in its entirety on the date on which the Conditions Precedent have been satisfied. Parties will do its outmost to fulfil the Conditions Precedent at the earliest possible. The Conditions Precedent include:[…]
at or before the 18th of September 2013
at or before the 30th of September 2013; […]
come into effect (Commencement Date);[...]
obligations hereunder, stated that the total liability of the Contractor (other than in respect of personal injury or death) for the first two operational years after signing of the Take Over Certificate, shall in no event exceed the amount of 25% (twenty five percent) of the Contract Price. After this period the total liability of the Contractor under this agreement shall in no event exceed the amount of 15% (fifteen per cent) of the Contract Price.[…]
Dear[B]
,
.”
inter alia, [B] and [F](from Amperax) the following email:
Please find the Design Evaluation Conformity Statement which we hold for this turbine.”
We kindly request the Type Certificate of the WTGs. It is requested for governmental project approval purposes.[...].”
Please find attached the Design Assessment Conformity Statement by Germanischer Lloyd which we hold for this turbine.[...].”
We have assumed that the Lagerwey turbines were having type certificate at the time of scheduling the work programme. Please be advised that we may encounter serious problems due to the lack of such certificate[...].”
In the last weeks, we have been informed with pieces of information and the challenges that the project (and the Project/Company Owner) faces and will assist where possible, however a Type Certificate cannot simply be obtained in short notice.
Secondly, thank you very much for the documents you've provided. However, please be advised that such documents are not sufficient in Turkey, and type certificate is still required.[...]
I'd like to clarify that despite our position as the sub-contractor, our main liabilities and duties against Meriç Enerji cover obtaining zoning and construction permissions, as well as completion of construction and electric mechanics works. And for such permissions, type certificate is required from us. We do our best endeavours in order to get such permissions without having the certificate, but it takes a lot more time and costs more as the same getting type certificates.[...]
I remind you the advance payment of 1.484.000 euro were made after the communication with Lagerwey Turkey, Mr. [B][sic]
according to finish your type certificate problem ASAP and reach opening date of the Power plant on 15. April 2016.[...].”
Contractor has and will provide technical documents to perform its obligations. A Type Certificate is not a technical document. It is not agreed that Contractor would supply Employer with a Type Certificate. Employer knows since 2013 that the Plant will be built and the need for a Type Certificate has not been discussed before. Employer has requested the DECS two months ago which has been provided[...].
Contractor is not in breach of contract and confirms to keep fulfilling its obligations under the agreement.[...].”
This is to inform you, that due to the reason you where not able to provide us with needed Certificate for Wind turbines during Edirne project, we have decided not to use Lagerwey for this environment. The decision had to be taken, for not loosing the permission of electricity production of our Company in Turkey. The delay and upcoming cost has to be covered from Lagerwey , therefore our Lawyers will get in touch with you to discuss the legal part. All parts which has produced due to Edirne project, we ask you to deliver to Prokon Hamburg storehouse.[...].”
3.The claim and the counterclaim
4.The considerations
opschorting). Either way, if Meriç, is right, Lagerwey breached the agreement and may be held liable for damages incurred by Meriç. If, however, Lagerwey’s argument is justified – as said above, that it was never agreed that it would take care of obtaining the type certificates – then Meriç’s claims would fail, and Lagerwey’s claims would become relevant.
each of the Parties acknowledges and confirms that it does not enter into this Agreement in reliance on any[…]
other undertaking by the other Party not fully reflected in the terms of this Agreement”. This supports Lagerwey’s view. However, as said above, the obligations of the parties are not merely determined by the wording of a clause, and so too here regarding this entire agreement clause, the relevant circumstances must be taken into consideration, particularly the earlier statements and conduct of the parties (See: Netherlands Supreme Court, 15 April 2013, ECLI:NL:HR:2013:BY8101,
Lundiform/Mexx).
all Legal Requirements[…]
for the execution of the Works”. However, the “Works” are defined in the Sales Agreement as meaning the works as specified in Annex 1. Obtaining a type certificate is not mentioned in that Annex and it is obvious that the “Works” relate to the WTGs (Lagerwey’s part of the deal) and not to providing energy to the Turkish grid (Meric’s responsibility) for which the certificate may have been needed.
of its obligations”under the agreement. However, a type certificate may be necessary for obtaining permission to provide energy to the Turkish grid, but providing energy to the Turkish grid was not an obligation of Lagerwey.
We want you to know that both type certificate and all kind of information and documents requested from us for Turkey electricity market regulatory board shall be pursued in time and full through our local company.”
pursued in time and full through our local company”), while Lagerwey Turkey would not have been able to obtain a type certificate, as it would have had to be obtained by the manufacturer, not being Lagerwey Turkey. If [B] did give any commitment, he did so on behalf of Lagerwey Turkey, not on behalf of Lagerwey, and Meriç was aware that [B] was not a representative of Lagerwey. Lagerwey also points out that there is no correspondence submitted between Lagerwey and Lagerwey Turkey that would support [B]’s power to bind Lagerwey.
many weeks beforeand
in another context, would not be covered. However, if it can be established that [B] did indeed send this letter, such could nevertheless be relevant for establishing whether Lagerwey agreed to provide a type certificate, not by virtue of [B]’s alleged letter as such, but for reason of supporting Meriç’s interpretation of Lagerwey’s obligations within the framework of possible other supporting circumstances. This is because the entire agreement clause may not be effective if Meriç could reasonably believe, in view of all circumstances, that Lagerwey would provide the type certificate and that the entire agreement clause would not apply to this obligation. The Court will therefore allow Meriç to prove that [B] sent the letter dated 8 August 2013. As to what extent [B]’s letter – if indeed sent – can be attributed to Lagerwey, the Court will decide after Meriç provided its evidence, in connection with all the other evidence.
During the negotiations, we discussed that it was a necessity for us that Lagerwey’s wind turbines were type certified several times. Mr. [A] for example raised this in a meeting on September 12, 2013, which took place in Barneveld. In that meeting, the Lagerwey representatives present at that meeting — Mr. Ard[the Court understands: Ard de Poot]
and Mr. Aart [D] — both informed us that the turbines consisted of such new technology that they were not type certified yet but ensured us they were working on it. As a result of this remark, Mr. [A] repeatedly asked for the type certificate and emphasized that the wind turbines could not be installed without the type certificate. The representatives of Lagerwey continuously replied that they would certainly obtain the certificate and that they were already working on it.”
recentcommitment given
within the contextof the agreement. It should be noted, however, that such an obligation of Lagerwey would only be a basis for Meriç’s claims if it entails that the type certificate would be provided no later than necessary for obtaining the governmental permit in time, as not getting the certificates in time was Meriç’s reason for terminating or suspending the Sales Agreement.