Uitspraak
1.DE PROCEDURE
2.DE VASTSTAANDE FEITEN
During the project it came up that there were severe problems that were not solved by you or your company. We have mentioned that in our weekly sub-contractor meetings, our letters to you and by email. These problems include: lack of quality of the paintjob, no supervision on site, not applying qualified workers, not applying more manpower, no covering of not to be painted surfaces including too late delivery of the renovated rooms to us/our client. Even the supervisors from the hotel have been visiting the weekly meetings and mentioned several times their concerns about the paint job. But no progress in the actions of your company in the days after these meetings (continuously) not finishing the job according to our schedule and meetings.
3.DE STANDPUNTEN VAN PARTIJEN
Awg. 294.229,64, vermeerderd met de wettelijke rente vanaf 29 maart 2017 tot de dag der voldoening en met veroordeling van GPSC in de kosten van de procedure.