Uitspraak
GERECHTSHOF DEN HAAG
Arrest van 6 oktober 2020
de vennootschap naar Duits recht HIK Systeme und Module GmbH,
Bosman Watermanagement B.V.,
Het geding
Beoordeling van het hoger beroep
25. The Purchaser shall without undue delay notify the Supplier in writing of any defect which appears. Such notice shall under no circumstance be given later than two weeks after the expiry of the period given in Clause 23. (...)
32. If, within a reasonable time, the Supplier does not fulfil his obligations under Clause 26, the Purchaser may by notice in writing fix a final time for completion of the Supplier’s obligations.
(…)
45. The contract shall be governed by the substantive law of the Supplier’s country.’
1/ organize a meeting with HIK and Bosman to come to mutual a point of view regarding the vibration analysis, risks of damage and possible solutions.
Simultaneously, the gearbox was fitted with new cogs to leave the 1:1 ratio, which presumably led to unwanted vibration characteristics in the machine and also limited the lifespan of the gears. During the installation of the new gears, it was noticed that they were already showing an enormous wear pattern after only a few months of operation. The pattern could very well indicate improper calibration of the gears. Looking at the gearbox design as it is, we even question the possibility of the current construction to reach the desired level of calibration. To support this hypothesis, only days after commissioning the machines with the new gears installed they started making alarming noises again.
On the 16th and 17th of December your mechanics concluded that this noise is caused by a wrongly adjusted lubrication system and by a wrong clearance of the cogs. Even more worrying is the fact that the newly installed gears are already showing wear signs within one week. This was observed and confirmed by your mechanics.
All of the above make us question the reliability and continuity of the Bosdox impellors. We urge you to review your design and come to a solution that does provide our customer with the required machine reliability and continuity. Furthermore, we request that you inform us (well-founded) about your intended solution at the shortest term possible.’
We have however now come to a point at which our customer is preparing a penalty for the ongoing problems and delays with the Bosdox units if we don’t come up with a stable solution coming Friday at it’s latest. As yet I can’t oversee the height of this penalty, we will however have no other choice than to transfer it directly to HIK.
Fortunately, I think there is still some time, but for this it is absolutely necessary that you come and visit us on Wednesday [dat is op 20 januari 2016; hof] and present your modifications to us. I will also inform our own engineering department to free up some time when you are here, so that they can also evaluate the revised design.’
Omdat alle gegevens bekend zijn bij jullie lijkt het ons handig dat jullie een geschikte koppeling gaan selecteren. Uitgangspunt moet wel zijn dat de asstompen zo kort mogelijk op elkaar komen te zitten zodat het benodigde lantaarnstuk zo kort mogelijk kan blijven. (…) Belangrijk is wel om te weten dat het tandwiel op de as van de rotor onderdeel is van de axiale ophanging van het draaiende gedeelte.
Graag even overleg hoe we het beste door kunnen pakken.’
Een arpex in onderstaande vorm is vrij kort is torsiestijf en laat qua uitlijning weer wel wat toe, maar is vrijwel niet te monteren in die opstelling. In die zin dus mooie oplossing, maar waarschijnlijk duur, lastig en gezien toerentallen ook niet echt nodig.
It has become impossible for us to run the project lik[e] this any longer. We are willing to give you until tomorrow to provide us with all the data we have asked for + answers to all questions asked. If not, we will be forced to pull the outstanding bank guarantee on your behalf.’
Diese müssen Woche 26 Fertig sein.’
Besteht die Möglichkeit, diese Messung ggf. in der 25. KW vorzunehmen? Die Messung sollte zu einem Zeitpunkt sein, wenn eine möglichst konstante Drehzahl der Ansteuerung möglich ist. Wann am Tag wäre das?
Des Weiteren benötigen wir die FU-Kennlinie; können Sie uns diese bitte zukommen lassen?’
Bitte kurzfristig Info! (…)’
Since you have again frustrated the project by not communicating about the manufacturing status of the lantern pieces, we have decided to take things in our own hands and manufacture these parts ourselves. These costs will al[l] be taken of the outstanding amount. HIK will not be needed anymore from this moment on. (…)’
So as I said yesterday, HIK is no longer needed, we will manufacture the needed parts ourselves, all costs will be taken off the outstanding invoices.’
In reconventie heeft Bosman (na eiswijziging) gevorderd:
primairbetaling, na verrekening, van € 48.511,37 exclusief BTW, met rente en kosten, en
subsidiairbetaling (zonder verrekening) van € 89.812,37 exclusief BTW, met rente en kosten. Aan haar reconventionele vordering heeft Bosman ten grondslag gelegd dat HIK is tekortgeschoten in de nakoming van de overeenkomst van opdracht van 27 februari 2015, waardoor zij een schade heeft geleden van € 79.650,21. Naar zij heeft gesteld, is haar daarnaast gebleken dat HIK de reparatie-opdracht van 27 november 2015 niet goed heeft uitgevoerd. Nadat HIK niet op haar sommatie tot herstel reageerde, heeft Bosman de reparatie zelf moeten (laten) uitvoeren, waarvoor zij € 10.162,16 aan kosten heeft gemaakt. Verder heeft zij buitengerechtelijke kosten moeten maken voor een bedrag van totaal € 1.673,12, aldus Bosman.
(i) de inhoud van het Duitse recht op dit gebied, in het bijzonder of naar Duits recht verzuim ook zonder ingebrekestelling kan intreden en, zo ja, onder welke
- ii) de inhoud van de op 1 april 2016 tussen partijen gemaakte nadere afspraken en de
- iii) welke betekenis in dit verband moet worden toegekend aan het verzoek van HIK bij haar e-mails van 9 en 21 juni 2016;
- iv) hoe de afgesproken leveringstermijn in de e-mail van 4 juni 2016 ‘Diese müssen Woche 26 Fertig sein’ moet worden uitgelegd; is daarmee bedoeld dat de productie van de lantaarnstukken in week 26 klaar moest zijn of dat in die week ook al levering en montage moest plaatsvinden.
Beslissing
- beveelt partijen in persoon, als het om een rechtspersoon gaat, deugdelijk vertegenwoordigd door een persoon die van de zaak op de hoogte is en bevoegd is om een schikking aan te gaan, vergezeld van hun raadslieden, voor het verstrekken van inlichtingen en het beproeven van een minnelijke regeling te verschijnen voor het hof in één der zalen van het Paleis van Justitie, Prins Clauslaan 60 te Den Haag, op 3 december 2020 om 11.00 uur;
- bepaalt dat, indien één der partijen
- verstaat dat het hof reeds beschikt over een kopie van de volledige procesdossiers in eerste aanleg en in hoger beroep, inclusief producties, zodat overlegging daarvan voor de comparitie niet nodig is;
- bepaalt dat partijen de bescheiden waarop zij voor het overige een beroep zouden willen doen, zullen overleggen door deze